Calendar resourcing

 

If you have come directly to this topic, you may first wish to review the topic Forecasting resources.

 

Steps to take before Calendar resourcing:

 

  1. Tick the box against the Worker you would like to resource to this task.
    Note: This is only applicable if the Worker has not been assigned to the task already.

  2. Edit the Days field to 0 for all worker assignments. (This is an essential step before using calendar resourcing).

 

Note: You may wish to add Generic users to the project team and use these for your initial resource plans.
             This allows you to forecast costs without allocating exactly who will be needed to complete the work.
             You can later replace the generic users with actual staff from the project team.

 

 

Note: At this point the Task Type will remain as Accumulated Work or Non Effort Driven.
             The Task Start and Finish dates are not relevant as long as the Resource Worker Days are set to 0.
             The Start and Finish date will update as soon as you start Calendar resourcing.

 

  1. Go to the Resources sub-menu within Project.

  2. Using the calendar Date picker, set it to the appropriate date from which you wish to start calendar resourcing.

  3. Depending on whether you calendar resource at a Daily, Weekly or Monthly level, set the drop-down selection as appropriate.

  4. Select whether to Sort by Task or Sort by User, this is purely a preference for how you wish to view your calendar resources.

  5. For the member of staff that you wish to resource, set the Percentage of the day, week or month you wish to apply the resource at.
    (For example Resource at 100% on daily to set the worker to work a full day, resource at 50% to set the worker to work a half day).

  1. Use the on screen cursor to click on the days/weeks/months you wish to assign the resource to work.
    Clicking a day turns that block to dark blue to show a resource assignment.

  2. Click on all days you wish to resource the user to.

  3. If you wish to remove a resource assignment, simply click the dark blue block and the assignment will be removed.

 

  1. Click Save when all updates have been made.

  1.  
     10. By clicking on the Detail action button at the top of the Resources screen or switching back to the Work Structure screen you can now see the updated task details.
  1.  

 

  1. The task Type will have changed to Movable Calendared - see below for further details.

  2. The task Constraint will have updated to Must Start On and become read-only.

  3. The task Start and Finish date will update automatically based on the earliest and latest resource assignment of any user resourced to the task.

  4. The Planned Work will have updated from the Calendar resource assignments and become read-only.

  5. The Resource Details Worker assignments will have updated and become read-only.

Movable Calendared vs Fixed Calendared

By default, when using calendar resourcing it will set the task Type to Moveable Calendared.

 

This means that even though you have specified exact resource assignments, you can still if desired change the task Start date and the resource assignments will move accordingly.

 

If you set the task Type to Fixed Calendared, the task Start and Finish date will become read-only, therefore preventing the manual adjustment of the task Start and End dates.

 

With Fixed Calendared, you can only change the dates by adding or removing resource assignments.

 

 

 

 