Comprehensive Job List

 

Group

Project

Description

Tabular report combining cost, revenue and profit information - including colour coded profit warnings. It enables comparison of budgeted, programme and actual figures

Business Purpose

Monitor the current profit of projects and inspect in detail the reasons for low or high profits

Ideal For

Project Manager

Director

Filters

Report Fields

Field Name

Description

Criteria

Project code

Project code

Entered in the project summary

Project name

Project name

Entered in the project summary

Task

Name of Task

Entered in the project work structure/gantt

Invoice Value

Value of invoice forecast for this task

Total predicted invoice value calculated from sum of invoice amounts to be generated by all fixed fee, time and expense invoice rules against the project, broken down by task

Invoiced to Date

Total of all invoiced items for this project

This column will total all invoice items that have been allocated to invoices created that are not in a 'draft' status.

Allocated Cost

Allocated budget cost for the project

Value taken from the budget column of project fee allocation

Target Profit Margin

Budgeted Profit for the project

Value taken from budget profit (%) column of project fee allocation

Programme Hours

Total estimated hours for the project

Taken from the Work Structure page (number of days allocated * number working hours per day)

Programme Hours Cost

Cost of total estimated hours for the project

Calculated from total number of allocated hours * sum of internal rate of all assigned workers to the project

Programme Expenses

Total estimated expenses on the project

Sum of all Expense Items allocated to the project (Expense Forecast page)

Total Programme Cost

Total cost value of estimated hours and expenses

Programme Hours cost + Programme Expenses

Actual Hours

Total approved hours submitted for the project

Sum of all hours submitted and approved by all workers on the given project

Actual Hours Cost

Cost of the total approved hours submitted for the project

This is calculated from each individual’s internal rate multiplied by their approved logged hours

Actual Expenses

Total Approved Expenses and Purchase Invoices submitted for the project

This is the net value of all approved Purchase Invoices and Expenses logged to the project

Total Actual Cost

Total cost of approved Timesheets and Expenses submitted

This is the sum of the Actual Hours Cost and the Actual Expenses

Remaining Cost

Remaining cost of the project.

Calculated by Programme Cost – Actual Cost

WIP

Work In Progress cost

Calculated by Total Actual Cost – Invoiced Items to Date

% Allocated Cost Used

Percentage used of the allocated cost of the project

Calculated by the Total Actual Cost / Allocated Cost

Profit

The current profit of the project so far

Calculated by Invoiced Total to date – Total Actual Cost

Profit Margin

Percentage representation of profit value

(Invoiced Total to date – Total Actual Cost) / Invoiced Total to date

 

 

 

 